View all Archives -
Environment and Development »
Competition in the U.S. Energy Industry
Table C-2. Estimated Capital Investment per
Annual Ton of Production at U.S. Coal Mines
| Underground
Mines |
Surface
Mines |
| Oper. year |
1970 |
1975 |
1980 |
1985 |
1970 |
1975 |
1980 |
1985 |
| Orig. cap. invest. |
$ 7.15 |
$ 8.46 |
$ 9.20 |
$ 9.84 |
$ 6.39 |
$ 7.33 |
$ 8.07 |
$ 8.78 |
| Tot. cap. invest. over
life of mine |
19.66 |
23.17 |
25.03 |
26.64 |
10.59 |
12.15 |
13.79 |
14.44 |
| Source: National Petroleum
Council, U.S. Energy Outlook, p. 145. |
|
|
time.
N.P.C.'s model projects a growth in coal demand of 3 percent a
year, so the figures for years beyond 1970 reflect average
capital costs for each year, assuming that new mines are added to
meet the demand growth and replace worked-out mines. Since the
model projects a 30-year life for each mine, capital costs should
presumably stabilize toward the end of the century at something
over $10 a ton of annual capacity for the original investment in
underground mines and over $9 a ton for surface mines. Since values
are expressed in constant 1970 dollars these two figures
should give rough estimates of capital investment requirements per
ton of annual output in that year. These figures are deficient in
several respects. An important deficiency is the failure to specify
the hypothetical mine sizes used in constructing the model's
investment figures.
We have
other fragmented data on capital investments required for entry
into coal mining. An unpublished Bureau of Mines study develops
data for hypothetical eastern underground mines operating in a
72-inch seam. The estimate assumes the investments will be made to
expand existing mines rather than to develop mines de novo.
Hence the figures omit capital costs involved in digging a shaft or
slope. Also since the model assumes the coal will be used as raw
fuel for a coal gasification plant, the data exclude costs of
erecting a cleaning plant. Based on 1972 costs, a mine with an
annual output of 1.13 million tons would cost $6.56 a ton of annual
output to erect and an additional $6.56 a ton for deferred capital
costs. At 3.12 million tons of annual capacity, the total
investment would be $15.3 million or $4.91 a ton of annual capacity
with an additional $15.7 million required for deferred capital
investment. Including investment to construct a cleaning plant and
to dig a shaft or slope would approximately double the capital
cost.
Taken
alone, the capital investment required for different sized mines
means little. It takes on added meaning, however, in light of the
Bureau of Mines' finding that the optimum scale plant (lowest
average mining cost per ton) was an underground mine with an annual
output rating of 3.8 million tons. This